Like for Like. The Home You Always Dreamed of. Again.

If you're rebuilding your home in the same area, footprint, and height (up to 110%), your project will typically be streamlined by city and county agencies. To move forward, you'll need to provide records of your existing home to the planning and building departments.

Site Clearing:

We connect you with our trusted partners for Phase 02 site clearing (After Phase 01 is signed off by EPA)

Estimated Schedule:

1 to 2 weeks

Estimated Cost:

30 to 100,000.00 depending on site size and configuration

Track 1: Design and Permitting

This is a turnkey solution to get you a custom design that fits into your existing envelop with new, code compliant construction.​

What's included:

Architecture design

Engineering (Civil, Structure, Soils, T-24 Energy)

Interior Design

Construction Permits

Estimated Schedule:

Track 1: Approximately 4 weeks plus permitting review time (estimated at 60 days)

Estimated Cost:

Track 1: $30.00/SF

​Track 2: Permitting Only

This solution is for those that already have a designer and only need help with the permit process

 

What's Included:

Engineering (Civil, Structure, Soils, T-24 Energy)

Construction Permits

Estimated Schedule:

Approximately 2 weeks plus permitting review time (estimated at 60 days)​

 

Estimated Pricing:

Track 2: $20.00/SF

Construction:

Schedule and cost vary based on deisgn

Find the support you need to rebuild your home after the devastating fires in Los Angeles. Our team is dedicated to helping you through this challenging time. Share your project details with us today, and let's work together to bring your home back to life.